DIMAPUR, NOVEMBER 5: Nagaland Governor, RN Ravi on Thursday reviewed ongoing road projects in the State. The projects reviewed included Kohima-Jessami road, Kohima-bypass road, Kohima-Mao road, Dimapur-Peren road and Changtongya-Longleng road.
In the meeting, it was revealed that Kohima-Dimapur 4-lane project works were slowed down due to rock sliding in several stretches of roads in during the past months.
The Governor reiterated to the contractors to expedite the ongoing work and to achieve the target, as assured by the contractors.
NHIDCL officials highlighted hiccups in certain districts resulting in stoppage of ongoing works for which the Governor asked the State Government to resolve the matter at the earliest.
The NHIDCL assured to finish the construction of the 2-lane road before December 15, 2020 along with the 4-lane Dimapur-Kohima road.
A Raj Bhavan release informed that roads being a priority area of concern, the Governor has been reviewing the status and progress of construction of the roads under NHIDCL.
Sentiyanger Imchen, ACS&FC (representing Chief Secretary), Rovilatuo Mor, Commissioner Nagaland, Mohammed Shihab Ali A, DC Kohima and NHIDCL senior officials and contractors were present at the review meeting.
The status and progress of NHIDCL road projects are available at the Nagaland Raj Bhavan website.
(Page News Service)